AchileionPayment Plan & Construction Schedule

Construction Schedule

 
 
 
 
 
 
Apartment
Stages of Payment
% of Purchase Price
Month
Estimated Timeline
Rs.
 
 
 
 
 
 
 
Seven Star
Luxury -
Colombo 4
**
Booking Deposit/Acceptance
of Offer Letter
1 Million
 
Immediate
1,000,000.00
 
 
 
 
 
 
 
 
1
Reservation & S&P Payment
30.00%
1
Jan-17
16,264,775.18
 
2
Completion up to cut podium ( first floor )
5.00%
13
Jan-18
2,877,462.53
 
3
Completion up to podium level 8
10.00%
19
Jul-18
5,754,925.06
 
4
Completion of E deck -Level 9
5.00%
22
Oct-18
2,877,462.53
 
5
Casting of Level 25 Floor Slab
10.00%
26
Feb-19
5,754,925.06
 
6
Casting of Level 40 Floor Slab
10.00%
30
Jun-19
5,754,925.06
 
7
Casting of level 48 floor slab
10.00%
33
Sep-19
5,754,925.06
 
8
Casting of helipad, Restaurant & Roof level slab
10.00%
34
Jan-20
5,754,925.06
 
9
Completion and handing over
10.00%
48
Dec-20
5,754,925.06
 
 
 
 
 
 
 